A company plans to migrate 300 interdependent servers. What is the best approach to sequencing?
- Exam domain
- Designing and planning a cloud solution architecture~25% of the exam
- Difficulty
- Medium
- In this mock
- 18 questions on this domainPractise this domain
Why the exam asks this
Creating a migration plan (i.e., documents and architectural diagrams).
Objective in the exam guide: Using migration methodologies, workload testing, network planning, and dependency planning.
Sequencing decides migration risk.
Why A is the answer
Map dependencies, group tightly coupled systems into waves, and test each wave before cutover
Dependency mapping and wave planning reduce risk; tools such as Migrate to Virtual Machines and Storage Transfer Service move workloads and data.
How it works
Migration follows assess, plan, deploy and optimize phases.
Dependency mapping groups systems that must move together into waves.
Tools such as Migrate to Virtual Machines and Storage Transfer Service move servers and data.
Clues in the question
The words that point to the answer, and what each one tells you.
- Interdependent servers
- Map dependencies.
In detail
- Start with low-risk waves to build skills.
- Plan network connectivity before the first wave.
Side by side with look-alikes
| Approach | Manages risk? |
|---|---|
| Dependency waves with testing | Yes |
| One weekend | No |
| Alphabetical | No |
| Critical first, untested | No |
Every option, checked
Knowing why each wrong option fails is how you rule it out on exam day.
A. Map dependencies, group tightly coupled systems into waves, and test each wave before cutoverRight
Dependency mapping and wave planning reduce risk; tools such as Migrate to Virtual Machines and Storage Transfer Service move workloads and data.
B. Move all servers in one weekendWrongMost tempting
One big move maximizes risk.
Why it tempts: It ends quickly. But any failure hits everything at once.
C. Move servers alphabeticallyWrong
Alphabetical order ignores dependencies.
D. Move the most critical system first with no testingWrong
Critical systems first, untested, is the riskiest start.
In practice
- Use Migration Center discovery data to build the dependency map.