A company plans to move its on-premises data warehouse to BigQuery. Before choosing tools, what should the data engineer do first?
- Exam domain
- Designing data processing systems~22% of the exam
- Difficulty
- Medium
- In this mock
- 15 questions on this domainPractise this domain
Why the exam asks this
Designing data processing systems: Designing data migrations.
Objective in the exam guide: Analyzing current stakeholder needs, users, processes, and technologies, and creating a plan to get to desired state.
Unplanned migrations fail. The exam checks the first step.
Why A is the answer
Assess current users, workloads and processes, for example with the BigQuery migration assessment, and create a plan
Migration starts by understanding stakeholders, workloads and requirements; the migration assessment estimates costs and effort and produces a plan.
How it works
A migration starts with current needs, users, processes and technologies.
The BigQuery migration assessment estimates storage costs and workload optimizations.
It produces a plan with the time and effort required.
Clues in the question
The words that point to the answer, and what each one tells you.
- Before choosing tools
- Assess and plan.
In detail
- Interview stakeholders about current and future needs.
- Plan validation criteria before moving data.
Side by side with look-alikes
| First step | Sound? |
|---|---|
| Assess and plan | Yes |
| Copy everything first | No |
| Largest reservation | No |
| Rewrite all reports | No |
Every option, checked
Knowing why each wrong option fails is how you rule it out on exam day.
A. Assess current users, workloads and processes, for example with the BigQuery migration assessment, and create a planRight
Migration starts by understanding stakeholders, workloads and requirements; the migration assessment estimates costs and effort and produces a plan.
B. Copy all tables to BigQuery and fix issues laterWrongMost tempting
Moving without a plan repeats old problems at new cost.
Why it tempts: It shows quick progress. But it moves waste and problems with the data.
C. Buy the largest reservation availableWrong
Capacity should follow measured needs.
D. Rewrite every report before moving any dataWrong
Rewriting everything first delays value and adds risk.
In practice
- Map each requirement, current and future, to a target component.