A team must install the operating system on 64 new compute nodes so all are identical and easy to rebuild. With NVIDIA Base Command Manager in place, what is the standard approach?
- Exam domain
- Control Plane Installation and Configuration19% of the exam
- Difficulty
- Medium
- In this mock
- 11 questions on this domainPractise this domain
Why the exam asks this
Control Plane Installation and Configuration (19% of the exam).
Objective in the exam guide: Install OS
Consistent OS installs are the base of the control plane.
Why B is the answer
Install the head node, then provision compute nodes from a managed software image
Base Command Manager streamlines provisioning: compute nodes boot and receive a consistent image from the head node.
How it works
The head node is installed first, often from installation media.
Base Command Manager streamlines cluster provisioning.
Compute nodes get their OS from managed images, so they match.
Clues in the question
The words that point to the answer, and what each one tells you.
- Identical and easy to rebuild
- Image-based provisioning.
In detail
- Changes go into the image, then roll out to nodes.
- Rebuilding a node is just reprovisioning it.
Side by side with look-alikes
| Approach | Consistent at scale? |
|---|---|
| Provision from managed image | Yes |
| Manual USB installs | No |
| Mixed cloning tools | No |
| User-chosen OS | No |
Every option, checked
Knowing why each wrong option fails is how you rule it out on exam day.
A. Let each user install their own OS versionWrong
Different OS versions break the cluster.
B. Install the head node, then provision compute nodes from a managed software imageRight
Base Command Manager streamlines provisioning: compute nodes boot and receive a consistent image from the head node.
C. Install the OS by hand on each node from a USB driveWrongMost tempting
Manual installs drift and take days.
Why it tempts: It works for one server. But 64 manual installs drift and take days.
D. Clone one node's disk with a different tool for each rackWrong
Mixed tools produce inconsistent nodes.
In practice
- Keep a known-good image version to roll back to.